BURLINGTON,
VT—June 30, 2016 The Vermont Agency of Transportation (AOT)
project manager calls the Shelburne Street roundabout project the
most difficult in his 17 year career because of the “spaghetti”
of utilities underground.
Engineer
Michael LaCroix, P.E. gave a “very likely“ roundabout
installation for 2020 at the high accident list intersection where
two pedestrian injuries were recorded during 2011-2014. when it rated
within the 17 highest pedestrian crash locations in Burlington.
LaCroix said he checked the crash performance of the three Route 15
Lamoille County roundabouts (Cambridge, Hyde Park, and Morrissville)
and found a 50% reduction in crashes. He pointed out that because of
the lower speeds at a roundabout that crashes which do occur are less
severe on average than those at signs or signals. The project
construction takes two years with the “hoped for” start in 2019
devoted to the utilities work and 2020 the actual construction of the
roundabout.
About 20
residents and Department of Public Works (DPW) staff attend the June
29 meeting where LaCroix agreed to periodic updates at the request of
City Councilor Karen Paul who explained that the project which goes
back to 2008 has been very difficult to get information about since.
In the most recent AOT report the intersection recorded 50 crashes
over five years.
LaCroix
said once the utilities plans are worked out with each utility
expected over the next months the regular steps of acquisition of
right-of-way occurs in 2017 and 2018 along with final design elements
take place. LaCroix stressed the project is a collaborative one with DPW where Laura Wheelock is project manager. LaCroix's unit is doing the design work. He
said the project is an “absolute” priority and continues as first
or second among the dozen projects assigned to his unit. LaCroix who meets with DPW every three months saw no reason that updates on project status can be done regularly.
Travel
time may be somewhat longer for those traveling St. Paul/Shelburne
Streets but less for those entering from the other three streets,
Locust, Ledge and South Willard.
About
half the cost of the $2-$4 million project involves underground
utilities work. Utilities include water, electric, at least two
cable lines, and Vermont Gas—all with various connections and
locations at the intersection involving five streets. Added to this
work are what might be termed pockets to take storm water runoff and
treat if before joining a pipe which directly enters Lake Champlain.
The 130
foot diameter roundabout will have on/off ramps for bicyclists on
each approach/exit to shared space with pedestrians so a cyclist has
the “choice” of taking the circular travel lane or switching to
pedestrian mode to move through the crossings then ramping down onto
to the street level again.
Tony
Redington, a member of the Technical Committee on the Walk Bike
Master Plan noted the two pedestrian crashes in four years at the
intersection and compared that to one crash in 50 years recorded at
five downtown Vermont roundabouts. “One would expect only about a
pedestrian crash once a decade with a roundabout,” said Redington,
also a roundabout expert and representative of Safe Streets
Burlington. He asked everyone to be careful walking at a roundabout
as with about 5,000 in place in the United States and Canada not a
single pedestrian fatality has been recorded to date.
There
are 12 public main streets and roads roundabouts in Vermont dating
from the first in 1995 but none in Chittenden County. The U.S. roundabout 2001 key safety study by the Insurance Institute for Highway Safety found a decrease of about 90% in serious and fatal injury rates after conversion to roundabouts. AARP advocates conversion of signals to roundabouts because of the higher rate of senior drivers fatalities at intersections compared to non-senior drivers. The average "busy" signalized intersection converted to a roundabout reduces pollutants, gasoline consumption and global warming gases generated at the intersection traffic by about 30%.